Abstract

The project plan of manpower replacement system based on web is to aim preparing
the system, supported tools and kinds of informations that be inputed in database on
internet so that some stakeholders”job seeker, company, higher education (to supply
experts)

and government as facilitator”can access the database system accurately,
relevant and on-time.
The project plan system had been done in Department of Manpower and Transmigration
that be used of guidance for measuring the system project modul with work breakdown
structure dan constructive cost model (Cocomo) so it is easy to make a project cost
proposal.
The result of calculation of the both approaches are the time schedule needs 7.68
months where the product design modul needs 1.23 months with experts are 2.49 manmonths,
the detailed
design
modul
needs
1.86
months
with experts
are
2.5
man-months,

the
code modul and unit test need 2.51 months with experts are
1.64 man-months.
The project plans can be concluded as follows : (1) can be known the results of
estimated calculation for experts and time each activity; (2) can be made the organization
chart included experts and their tasks; and (3) can be made the time schedule.

Keywords

work breakdown structure constructive cost model

Article Details

How to Cite
Martono, A. (2012). Perencanaan Sistem Database Penempatan Tenaga Kerja Berbasis Web dengan Pendekatan Work Breakdown Structure dan COCOMO. Rekayasa Teknologi, 4(2). Retrieved from https://journal.uhamka.ac.id/index.php/rektek/article/view/117